CAT 2019 Slot 1 QA Q30 Time & Work

Question 30 of the Quantitative Ability (QA) section, CAT 2019 Slot 1, with CAT's official answer.

Three men and eight machines can finish a job in half the time taken by three machines and eight men to finish the same job. If two machines can finish the job in 13 days, then how many men can finish the job in 13 days? [TITA]

TITA: type in the answer. There are no options and no negative marking.

Answer: 13 Time & Work TITA

A worked solution for this question is being written. Meanwhile, practise it in a timed mock and see how other aspirants did.